OC stands for occupancy certificate. It is issued by the local planning authority after a building is finished, and it certifies that the building was built as per the approved plan and is fit for occupation. Without it, moving in is not legally allowed in most cities, permanent water and power connections can be refused, and resale and loans become difficult.
The OC is the single most important document on a ready home, and the one most often missing. This guide explains what it proves, how it differs from a completion certificate, who issues it in Telangana, Tamil Nadu and Karnataka, how to check a real one, and what you can do if the developer has not obtained it.
- Full form: occupancy certificate. Some states call the same approval a completion certificate or a completion-cum-occupancy certificate.
- Issued by: the authority that approved the building plan, such as the Hyderabad city corporations or HMDA, CMDA, DTCP or the corporation in Chennai, and the city corporation or BDA in Bengaluru.
- Who applies: the developer or owner, after construction is complete.
- Under RERA, the developer must obtain it and give it to the buyers or their association.
- After the OC, RERA requires the buyer to take possession within two months, and the developer to execute the conveyance within the period set by local law, or within three months if the law sets none.
- No GST is charged if you pay the whole price after the completion or occupancy certificate is issued.
What does an occupancy certificate prove?
The authority inspects the finished building and confirms that it matches the sanctioned plan: the number of floors, the setbacks, the parking, and the use. It also checks that the fire, lift, structural and sanitary approvals are in place. The OC is the authority’s confirmation that people may live in the building.
An OC usually states the building permit number, the property address, the number of floors and units, the date of issue, and any conditions.
What is the difference between OC and CC?
| Completion certificate (CC) | Occupancy certificate (OC) | |
|---|---|---|
| What it says | Construction is finished as per the approved plan | The building is fit to occupy |
| When | On completion | On completion, after inspection and other NOCs |
| Why buyers need it | Proof the building matches its approval | Legal right to move in; needed for utilities, loans and resale |
| In practice | Many authorities issue one combined certificate. What matters is that the authority has certified the building complete and fit to occupy. | |
CC can also mean commencement certificate, issued before construction starts. Do not confuse the two: a commencement certificate says nothing about the finished building.
Who issues the OC in Hyderabad, Chennai and Bengaluru?
| City | Usual issuing authority | What to know |
|---|---|---|
| Hyderabad and Telangana | The Hyderabad city corporations (GHMC, Cyberabad, Malkajgiri), HMDA, or the municipality or gram panchayat, depending on who approved the plan | Building permissions and occupancy are handled online through the state’s building permission systems. Check the permit number on the OC against the original approval. |
| Chennai and Tamil Nadu | CMDA for larger buildings in the Chennai Metropolitan Area; the Greater Chennai Corporation or local body for smaller ones; DTCP and local bodies outside CMA | Tamil Nadu’s building rules call it a completion certificate, and Rule 20 requires it before power, water and sewer connections. Since a March 2024 amendment, small residential buildings up to 14 m high with no more than eight homes or 750 sq m are exempt. A flat in a larger apartment building needs one. A separate third-party certification route for small buildings, added in October 2026, is about approvals, not an exemption from the certificate. |
| Bengaluru and Karnataka | One of the five city corporations under the Greater Bengaluru Authority, BDA, or the local planning authority | The rule on OCs for power connections has changed several times. After Supreme Court directions in December 2024, BESCOM tightened new connections in 2025. In June 2026 Karnataka gave a one-time relaxation for homes on plots up to 2,400 sq ft (ground plus three or stilt plus four floors) completed by 31 May 2026. For an apartment, insist on the OC. Check the OC against the sanctioned plan and the khata. |
The rule of thumb: the authority that approved the building plan issues the OC. If you do not know which authority approved the project, find out how to check HMDA, DTCP, CMDA and BDA approvals.
How do you check whether a building has an OC?
- Ask the developer or seller for a copy, along with the sanctioned building plan.
- Match the details: the permit number, survey number, address, number of floors and number of units should be the same on the plan and the OC.
- Check the authority’s records. Most authorities let you search approvals and certificates online by permit or file number. If you cannot find it, write to the authority or ask your lawyer to check.
- Check the project on the state RERA website. Developers upload completion and occupancy certificates there for registered projects.
- Look at the floors. If the building has more floors than the OC or plan shows, the extra floors are not covered.
- For a resale home, ask for the OC of the building, not only the seller’s sale deed. Older buildings may have a partial OC that covers some blocks only.
What happens if a building has no OC?
- Living there may be unauthorised, though the rules and exemptions differ by state and building size. The authority can issue notices, and in serious cases act against the building.
- Utilities: permanent water, sewer and power connections can be refused, leaving residents on temporary or construction supply.
- Home loans: many banks will not lend on a ready home without an OC, which also makes resale harder.
- Property tax may be assessed at a higher or penal rate in some cities. See how property tax works in Hyderabad and Bengaluru.
- GST: when you buy from a developer, any part of the price paid before the completion or occupancy certificate is issued carries GST. A resale between owners has none.
What are your rights if the developer has not obtained the OC?
Under the RERA Act, 2016, the developer is responsible for obtaining the completion and occupancy certificates and handing them to the buyers or their association. If the developer offers possession without an OC, or delays it, you can:
- Refuse possession until the OC is issued, and write to the developer saying so.
- File a complaint with the state RERA authority for compensation or interest for delay, or a refund if you want to withdraw.
- Approach a consumer commission. The Supreme Court has held that a developer’s failure to obtain an OC is a deficiency in service.
Possession without an OC is a common reason buyers lose money years later. The 15 checks before you pay a booking amount include the OC for ready homes.
What is a partial OC?
In large projects built in phases, the authority may issue an OC for the towers or villas that are complete while others are still being built. A partial OC is valid for the blocks it names. Check that your block and unit are listed, and that common facilities such as the clubhouse, sewage treatment plant and fire systems serving your block are covered.
Which other documents go with the OC?
| Document | Why it matters |
|---|---|
| Sanctioned building plan | What the OC is checked against |
| Commencement certificate | Construction started with permission |
| Fire NOC | Required for high-rise buildings before the OC |
| Lift licence | Lifts were inspected and licensed |
| Possession letter | The date you took the home over, which starts the five-year defect liability under RERA |
| Conveyance or sale deed | Transfers ownership; under RERA, within the period set by local law, or three months after the OC if none is set |
For the full buying sequence, see how to buy a house in India in 12 steps. For what the area numbers on the OC and plan mean, read carpet area vs built-up area.
Questions about the occupancy certificate
What is the full form of OC in real estate?
OC stands for occupancy certificate. It is issued by the local planning authority once a building is complete, confirming it was built as per the approved plan and is fit to occupy.
What is the difference between OC and CC?
A completion certificate (CC) confirms construction is finished as per the approved plan. An occupancy certificate (OC) confirms the building is fit to live in. Many authorities issue a single combined certificate. CC can also mean commencement certificate, issued before construction starts.
Who issues the occupancy certificate?
The authority that approved the building plan: the Hyderabad city corporations, HMDA or the local body in Telangana; CMDA, DTCP or the local body in Tamil Nadu, where it is called a completion certificate; and the city corporation, BDA or local authority in Karnataka.
Can I buy a flat without an OC?
You can buy an under-construction flat before the OC is issued, but do not take possession of a ready flat without one. Living in a building without an OC can be unauthorised, and loans, utilities and resale become difficult.
Is GST payable on a home bought after the OC?
Not if you pay the whole price after the occupancy or completion certificate is issued. Any payment made before the certificate carries GST.
What can I do if the builder does not give the OC?
Refuse possession in writing, and file a complaint with the state RERA authority for interest, compensation or a refund. You can also approach a consumer commission; the Supreme Court has held that failing to obtain an OC is a deficiency in service.
How do I check if the OC is genuine?
Match the permit number, address, floors and units on the OC with the sanctioned plan, then check the certificate in the authority’s online records or on the project’s RERA page. A property lawyer can confirm it with the authority.
What is a partial occupancy certificate?
An OC issued for the completed blocks or towers of a project while other phases are still being built. It is valid only for the blocks it lists, so check your unit is covered.
About this guide: Published by Urbanrise, a real estate developer, as general information for homebuyers. It is not an advertisement or an offer for any project.
Sources
- Developer’s duty to obtain the occupancy certificate, possession within two months and conveyance within three months: Sections 11(4)(b), 17 and 19(10) of the Real Estate (Regulation and Development) Act, 2016.
- Failure to obtain an OC as deficiency in service: Supreme Court of India, Samruddhi Co-operative Housing Society v. Mumbai Mahalaxmi Construction, 2022.
- Telangana building permissions: GHMC and HMDA.
- Tamil Nadu completion certificate: Rule 20, Tamil Nadu Combined Development and Building Rules, 2019, CMDA.
- GST on construction services: CBIC.
Swati is a real estate editor with 10 years of experience. She covers housing markets, home buying and property rules for Indian homebuyers. This page is general information, not legal, tax or investment advice.